The City of Rialto, acting through Veolia Water West Operating Services, Inc., is soliciting design‑build proposals to construct two new Pressure Reducing Valve (PRV) stations that will regulate water pressure between Pressure Zones 2 and 3A. The contractor must provide complete engineering, civil, and construction services, including site work, pipe installation, equipment pads, and commissioning, and must deliver the project within a 270‑day schedule.
• Design‑build scope covering 30 % (pre‑design), 60 % (intermediate) and 100 % (final) design phases, plus construction and commissioning.
• Required deliverables: detailed drawings, specifications, construction schedule, QA/QC documentation, as‑built records, O&M manuals, and warranties.
• Mandatory pre‑bid site walk on May 12, 2026; RFI deadline May 21, 2026; bid submission deadline May 28, 2026.
• Contract value estimated at $650,000; performance bond, bid bond (10 %), and 10 % retention apply.
• Project must be completed by April 30 2027, with liquidated damages of $1,500 per day for overruns.