The City of Marion is seeking contractors to repair and replace municipal sidewalks using Portland cement concrete (PCC). The scope includes approximately 3,891 square feet of sidewalk—3,123 SF of 4‑in. PCC and 768 SF of 6‑in. PCC—covering demolition (if required), concrete placement, finishing, traffic control, and site restoration per municipal specifications. Four bidders submitted unit‑price bids, with the lowest combined total matching the engineer’s estimate of $68,400. The contract will require a 10 % bid‑surety bond and acknowledgment of any addenda.
• Total concrete area: 3,891 SF (4‑in. and 6‑in. sections).
• Unit‑price bids ranged from $16/SF to $25/SF for the 4‑in. thickness.
• Minimum bid (Horak Concrete) equals the engineer’s estimate at $68,400; highest bid (Central States Concrete) $98,811.
• All bidders must provide a 10 % surety bond and have acknowledged any addenda.
Attached files
Similar opportunities
Matched by Bid Banana AI™
Bid Banana · 1.6M+ bids and awards 🍌
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.