The City of Clinton is seeking a contractor to provide traffic signalization services for two intersections: So. 2nd St. & 2nd Ave. So. and So. 2nd St. & 5th Ave. So. The project includes the installation of pole foundations, poles, arms, wiring, conduit, heads, signs, detection equipment, traffic signal control equipment, and associated appurtenances. The contractor will also be required to remove and replace existing traffic signals and signage. The engineer's estimate for the project is $425,000. The project is expected to start on July 16, 2026, and be substantially completed by December 15, 2026.
• The project includes traffic signalization of two intersections
• The contractor will be required to install pole foundations, poles, arms, wiring, conduit, heads, signs, detection equipment, and traffic signal control equipment
• The contractor will also be required to remove and replace existing traffic signals and signage
• The engineer's estimate for the project is $425,000
• The project is expected to start on July 16, 2026, and be substantially completed by December 15, 2026