The National Park Service is seeking a qualified contractor to demolish an existing double‑vault toilet at Badwater Basin (Death Valley NP) and install a new precast concrete double‑vault restroom that meets ADA, “sweet smelling” technology, and extreme‑heat design requirements. The contractor must provide all labor, equipment, demolition, disposal, excavation adjustments, back‑filling, grading, and final installation within 180 days of award, and must submit detailed product data, warranties, safety plans, insurance certificates, and a project schedule. The work includes delivering a single precast unit, installing steel doors, windows, signage, grab bars, toilet accessories, a 1000‑gallon vault liner, ventilation, solar lighting, and a baby‑changing station, while adhering to IBC, ASTM, ACI, and NPS safety and environmental standards.
• Demolition and removal of existing 126 sq ft double‑vault toilet
• Supply and install one precast concrete double‑vault restroom (ADA‑compliant)
• Provide all site preparation, excavation, back‑fill, grading, and finishing work
• Deliver and install doors, windows, signage, toilet accessories, vault liner, vent pipe, solar kit, and optional baby‑changing station
• Meet IBC 2003+, ASTM C33/C39/C143/C150/C192, ACI 1211.1, PCI MNL 116, ADA, and “sweet smelling” technology standards
• Submit product data, warranties, insurance, safety & spill‑prevention plans, and project schedule with the quote
• Complete work within 180 days; payment is a lump‑sum upon final completion