The Gwinnett County Board of Education is soliciting sealed bids for the re‑roofing of four K‑12 school buildings (Walnut Grove Elementary, Central Gwinnett High, Collins Hill High, and North Gwinnett High). The contract will be awarded on a stipulated‑sum basis, with mandatory pre‑bid conference attendance and a strict bonding requirement (5 % bid bond, 100 % performance and labor‑material bonds). Bidders must be Georgia‑licensed contractors and submit a completed AIA A305 qualification statement. Work is scheduled to begin May 27 2027 and be substantially complete by July 23 2027.
• Scope: Complete removal and replacement of roofing systems on four school buildings.
• Location: Suwanee and Lawrenceville, GA.
• Mandatory pre‑bid conference: Oct 29 2026, 9:00 a.m., multiple school sites.
• Bid submission deadline: Nov 12 2026, 3:00 p.m. ET (sealed bids at Board of Education office).
• Bonds required: 5 % bid bond; 100 % performance and labor‑material payment bonds.
• Qualification: Georgia contractor license + AIA A305 statement.
• Project timeline: Mobilization within 10 days of notice to proceed; work duration ~57 days.
You found this one. Bid Banana has 1.6M+ bids and awards.
You found this bid by looking. Bid Banana searches open government bids across all 50 states, updated daily, so you stop hunting: save a search once and we email you your new matches, daily or weekly.