This solicitation seeks a qualified general contractor to design and construct a new traffic‑signal system at the intersection of NW 82 St and NW 114 Ave in Doral, FL. The work includes full traffic‑signal installation (mast arms, poles, signal heads, controllers, video detectors), roadway signing, pavement markings, maintenance‑of‑traffic (MOT) during construction, site preparation (clearing, grubbing, earthwork), concrete curb & gutter, sidewalks, and related utility work. The contract is a fixed‑price, 180‑day performance agreement with liquidated‑damages provisions for late completion.
• Scope covers full traffic‑signal hardware, civil works, and related signage/markings.
• Contractor must provide a 5 % bid bond, 100 % performance and payment bonds, and meet all insurance, safety, and regulatory requirements (OSHA, FHWA, Buy‑America, etc.).
• Mandatory pre‑bid virtual meetings on May 27 2021 and June 18 2021; questions due June 3 2021.
• Project duration is 180 calendar days from contract execution; liquidated damages of $1,665 per day after substantial completion.
• The original solicitation was cancelled on July 20 2021; a re‑advertisement is expected in the near future.