The City of Palm Bay, Florida, issued a Request for Proposal (RFP) for the road reconstruction of three locations: Malabar at Jupiter intersection, San Filippo at Waco intersection, and Community College Parkway. The project involves full depth reclamation, drainage work, and paving. The contractor is responsible for furnishing and installing all parts of the project as shown on the project plans and bid quantities. The contract was awarded to Asphalt Paving Systems, Inc. for a total price of $711,145.00.
• The project includes three locations: Malabar at Jupiter intersection, San Filippo at Waco intersection, and Community College Parkway.
• The contractor is responsible for full depth reclamation, drainage work, and paving.
• The contract was awarded for a total price of $711,145.00.
• The contractor must furnish and install all parts of the project as shown on the project plans and bid quantities.
• The project requires the contractor to perform various tasks, including surveying, dewatering, temporary striping, temporary business signs, temporary signs, utility coordination, signal adjustment coordination, relocation as required with utility companies, disposal of materials, and relocation or installation of materials within the project limits.