This contract concerns the complete demolition of existing structures at 1306 Congress St, Mobile, AL, using a wet‑method approach to control lead‑based paint dust, and includes site clean‑up, vegetation removal, utility line capping, erosion‑control BMPs, hazardous waste disposal, and post‑demolition documentation. The city will award the work on a fixed‑price basis to a qualified contractor who can meet environmental, safety, and insurance requirements and complete the job within a tight 30‑day performance window.
• Wet demolition of all structures, footings, slabs, and associated debris, with LBP/ACM handling.
• Mandatory erosion and sediment control, utility capping, and final site stabilization/seeding.
• Contractor must provide E‑Verify enrollment, insurance, and post‑completion deliverables (photos, waste records, newspaper notice).
• Performance schedule: quotes due 17 Jul 2024, NTP issued after contract documents, work start within 3 business days, substantial completion in 30 calendar days, liquidated damages $250/day for delays beyond 15 days.