The contract is for the upgrade and repair of the auditorium stage floor at Topeka High School. The scope of work includes sanding and refinishing the existing pine stage floor, as well as removing and replacing the entire pine floor, nine floor box covers, and the floor trap to the existing concrete deck. The contract was awarded to Acme Floor Co, Inc. and JP Construction, LLC, with a total bid amount of $86,228.00. The contract includes a base bid and an add alternate, with a $20,000 allowance for field changes. The work is to be completed at Topeka High School, with a minimum charge of $1,061.00 for unit price 1 and $1,500.00 for unit price 2.
• The contract includes a base bid and an add alternate
• The work is to be completed at Topeka High School
• The contract includes a $20,000 allowance for field changes
• The minimum charge for unit price 1 is $1,061.00 and for unit price 2 is $1,500.00
• The contract was awarded to Acme Floor Co, Inc. and JP Construction, LLC