This contract is for the asset management valve replacement at Parque La Paz (Arnold Manor) in Goodyear, Arizona. The contract was awarded to TF Contracting Services and has a duration of 94 days, starting on December 16, 2024, and ending on March 31, 2025. The contract includes various tasks such as preconstruction phase, construction phase, and pavement restoration and final cleanup. The contract amount is approximately $384,257.43. Key aspects of the contract include:
• Preconstruction phase: 11 days
• Construction phase: 82 days
• Pavement restoration and final cleanup: 7 days
• Contract amount: $384,257.43
• Vendor: TF Contracting Services
• Agency: City of Goodyear