This contract awards a single‑vendor stipulated‑sum agreement to remove a nuisance‑abated structure at 7123‑A Smith Street, Mobile, AL. The scope requires wet demolition of the building and all foundations, utility disconnection, full debris and hazardous‑waste (lead‑based paint, asbestos) disposal, erosion‑control BMP installation, site stabilization, reseeding/landscaping, and final notice‑of‑completion publication. The contractor must provide proof of E‑Verify enrollment, insurance, and business licensing, and must complete the work within 15 calendar days of receiving a Notice to Proceed, with liquidated damages of $250 per day for overruns.
• Wet demolition and complete removal of footings, slabs, CMU/brick, and related structures.
• Hazardous‑material handling (LBP/ACM) with proper disposal documentation.
• Installation of temporary and permanent erosion‑control measures, followed by seeding and mulching of disturbed areas.