This contract involves the complete demolition and site clean‑up of a hazardous structure located at 777 Welworth Street, Mobile, AL. The city requires wet demolition of all existing building components, capping of utility lines, removal of debris, and strict environmental controls (erosion, sediment, lead‑based paint, asbestos). The contractor must supply proof of E‑Verify enrollment, insurance, and a stipulated‑sum agreement, and deliver all close‑out documentation within 30 calendar days of receiving the Notice to Proceed. The project is funded by the City of Mobile and will be performed under a strict schedule to avoid liquidated‑damages and daily late‑work charges.
• Perform wet demolition of all structures, including foundations, slabs, and minor vegetation.
• Implement erosion & sediment controls and comply with lead‑based paint/asbestos BMPs.
• Provide required pre‑award documentation (E‑Verify, insurance, AIA forms) and post‑completion close‑out items within the 30‑day window.