The City County Building Roof Replacement contract was awarded to Kalkreuth Roofing and Sheet Metal, Inc. for a total of $1,946,120. The contract is for the removal of the existing roof and the installation of a new multiple-ply modified bitumen roofing system. The contract duration is 120 days, and the work is expected to be completed by May 1, 2022. The contract includes provisions for asbestos abatement and requires the contractor to maintain liability insurance. Key aspects of the contract include:
• The contract is a fixed-price contract, with a total value of $1,946,120.
• The contractor is required to commence work within 7 days of the notice to proceed and complete the work within 120 days.
• The contract includes provisions for asbestos abatement and requires the contractor to maintain liability insurance.
• The contractor is required to provide labor, materials, and equipment for the removal of the existing roof and the installation of a new multiple-ply modified bitumen roofing system.
• The contract includes a contingency fund of 10% of the base bid.
• The contractor is required to make available to the Councils of Government, Municipalities, and School Districts within Allegheny County the goods and services contained within this agreement at the prices quoted under this contract.