This contract is for pavement repairs on a section of the Maine Turnpike, from mile marker 0.0 to 109.10. The work includes milling and paving, as well as other incidental work such as sweeping and excavation. The contract was awarded to Coastal Road Repair, LLC, and the completion date is October 1, 2025. The Maine Turnpike Authority is responsible for traffic control and maintenance of traffic during the project.
• The contract includes a variety of pay items, such as hot mix asphalt, bituminous tack coat, and curb work.
• The contractor is required to follow the Maine Department of Transportation Standard Specifications and the Maine Turnpike Authority's Supplemental Specifications.
• The contract includes a provision for mobilization, which includes preparatory work and operations necessary to move personnel, equipment, and supplies to the project site.
• The contract also includes a provision for maintenance of traffic, which is the responsibility of the Maine Turnpike Authority.