This contract is for the East District Restroom Updates project, which involves renovating restrooms to make them ADA compliant. The contract was awarded to Café Construction & Development, Inc. for a total amount of $146,530. The project is expected to be completed within 365 consecutive calendar days from the start date. The contractor is required to comply with M/WBE subcontracting requirements and provide written notification to the County's Project Manager when 90% of the total contract amount has been reached. Some key aspects of the project include:
• Renovating restrooms to make them ADA compliant
• Managing, scheduling, demo, layout, cutting concrete floor, repouring floors, laying new block walls, demoing doors, installing new doors, installing tile, installing drop ceiling, hauling off debris, cleaning, and punch out at final
• Compliance with M/WBE subcontracting requirements
• Providing written notification to the County's Project Manager when 90% of the total contract amount has been reached