This contract is for the rehabilitation of the E 18th Street trunk sewer in Vancouver, Washington. The contractor, Allied Plumbing and Pumps, LLC, will furnish and install approximately 3763 lineal feet of 27-inch and 1980 lineal feet of 30-inch Cured-In-Place Pipe (CIPP) to rehabilitate existing sanitary sewer mains. The work includes customer notification, bypass pumping, cleaning, root and sediment removal, initial Closed Circuit Television (CCTV) inspection and assessment, CIPP installation and testing, reinstatement of all laterals, testing, and final CCTV inspection. The contract also includes epoxy or polyurethane lining of 18 manholes of various depths for corrosion prevention. The work shall be physically complete within 40 working days from the Notice to Proceed.
• The contract value is $2,715,625.15 USD.
• The contractor is required to provide insurance coverage, including commercial general liability, commercial automobile liability, and workers' compensation.
• The contractor is required to comply with all federal, state, and municipal laws, rules, and regulations.
• The contract includes a dispute resolution process, which includes mediation and litigation.
• The contract has a termination clause, which allows the City to terminate the contract for convenience or for cause.