This RFQ seeks a qualified contractor to perform a full “wet‑method” demolition of the structures located at 771 Farnell Street, Mobile, AL 36606, including utility disconnection, hazardous‑material handling, erosion control, and site restoration. The work must be completed within a tight schedule and meet extensive environmental and safety regulations.
• Scope includes demolition of all building components, capping of sewer, water, and gas lines, removal of debris, and permanent site stabilization (seeding, mulching).
• Contractor must provide proof of E‑Verify enrollment, certificates of insurance, and adhere to strict lead‑based paint and asbestos disposal protocols.
• Liquidated damages of $250 per day apply after 45 days from Notice to Proceed; substantial completion is required within 30 days of start.