This contract is for the replacement of siding, insulation, windows, and doors at the Burnett Administrative Center. The project is divided into several phases, with the base bid covering the northeast elevations of Pod C/F. The contract also includes several add alternates, which cover additional work such as removing and replacing existing windows, siding, trim, and plywood sheathing from other areas of the building. The contractor is required to provide all materials and labor to complete the project per the plans. The contract also includes a lump sum allowance for any unforeseen physical conditions requiring repairs to the interior and exterior surfaces of the building.
• The base bid scope of work includes removing and replacing existing windows, doors, siding, trim, and plywood sheathing from the northeast elevations of Pod C/F.
• The add alternates cover additional work such as removing and replacing existing windows, siding, trim, and plywood sheathing from other areas of the building.
• The contractor is required to provide all materials and labor to complete the project per the plans.
• The contract includes a lump sum allowance for any unforeseen physical conditions requiring repairs to the interior and exterior surfaces of the building.
• The total awarded amount for the contract is $536,200.00.