This contract is a fixed‑price, wet‑demolition and site‑cleanup project for a nuisance‑abated property at 5014 Perin Road, Mobile, AL. The City of Mobile’s Municipal Enforcement Department solicited sealed‑envelope quotes, selected a single vendor, and required comprehensive demolition, utility capping, hazardous‑material handling, erosion‑control BMPs, and post‑demolition landscaping. All work must be finished within 15 days of receiving the Notice to Proceed, with a $250 per day liquidated‑damage penalty for late completion. The contractor must also provide extensive documentation, including photographs, waste‑shipment records, insurance certificates, and a newspaper notice of final completion.
• Wet demolition of wood‑frame structures, footings, slabs, and associated debris.
• Mandatory utility disconnections, lead‑based paint/asbestos disposal, and erosion‑control BMP installation and maintenance.
• Required post‑demolition seeding, mulch, and final close‑out affidavits before final payment.