The contract involves the installation of motor-operated actuators on four isolation valves in the chilled and hot water piping serving the Main Jail. The estimated construction cost is $85,000. A mandatory pre-bid conference and walk-through were held, and attendance was required for all bidders. The contract requires a contractor's license, and mandatory background checks were required for all attending personnel. Key aspects of the project include:
• Installation of motor-operated actuators on four isolation valves
• Estimated construction cost of $85,000
• Mandatory pre-bid conference and walk-through
• Requirement for contractor's license and background checks