The contract is for the construction of a 1600 SF addition to the existing La Porte EMS Headquarters. The addition will be located on the east side of the existing building and will require some alterations to the existing parking lot. The contract includes various items such as site preparation, traffic control, selective demolition, storm water pollution prevention, trench safety, building addition, and site work. The contract was awarded to multiple vendors, including Construction Masters, Dunhill Development of Houston, Inc, General Contract Services, Inc, Nash Industries, Inc, and Tucon, LLC. The total base bid for the contract is around $1 million.
• The contract includes a pre-bid conference and a site visit.
• The contract has multiple addendums, including Addendum No. 1, Addendum No. 2, Addendum No. 3, Addendum No. 4, and Addendum No. 5.
• The contract has a bid tabulation section, which lists the bids from each vendor.
• The contract has a description section, which provides a detailed description of the project.