This contract calls for the demolition, vapor‑barrier replacement, installation of new finish flooring, full wood‑floor refinishing, and repainting of court lines (including a new center logo) in the Illing Middle School gymnasium. The work must be completed within a tight 12‑day window in August 2026, adhering to Connecticut building, ADA, OSHA, and fire‑safety codes, and includes a one‑year warranty on materials and workmanship. The agency requires comprehensive insurance, living‑wage certification (if applicable), and strict site security measures.
• Scope: demo, vapor‑barrier, new floor, full refinish, line painting, Bona Elite coating.
• Schedule: walk‑through 1 July 2026 → proposals due 10 July 2026 → work 10‑21 August 2026.
• Procurement: open RFP, no bonds, 5 % retainage, evaluation based on experience, prior MPS work, quality, price, completeness, and references.