The contract is for the construction of a traffic signal at the intersection of Main Street and Sultana Street/Timberlane Avenue. The scope of work includes the construction of asphalt concrete pavement, concrete curb, concrete gutter, concrete sidewalk, ADA facilities, striping, and traffic signal installation. The contract was awarded to DBX, Inc. for an amount of $1,665,171.00. The pre-bid conference was held on June 4, 2024, and the bid submission date was June 24, 2024.
• The contract documents include drawings, cost estimates, and addendums.
• The contractor is required to acknowledge the addendums and provide bid security.
• The contract is administered by the City of Hesperia, with Eydee Jimenez as the Deputy City Clerk / Project Manager.