Awarded vendors
- Medley Sports Construction
Description
The City of Clermont has awarded a contract for the resurfacing of the Lake Felter Basketball Court. The contract, valued at $69,950, was awarded to Medley Sports Construction. The work is to be completed within 90 consecutive calendar days from the commencement date of March 4, 2024. The contract includes a provision for liquidated damages of $300 per day for each day the work remains incomplete after the completion date. Key aspects of the contract include:
• The contract amount is $69,950.
• The contract duration is 90 consecutive calendar days.
• The completion date is May 2, 2024.
• Liquidated damages of $300 per day will be assessed for each day the work remains incomplete after the completion date.
This contract is for a specific construction project, and the terms and conditions are tailored to the needs of the City of Clermont and the vendor.