The City and County of Denver’s Department of Transportation and Infrastructure (DOTI) awarded a maximum‑value hard‑bid contract for city‑wide concrete panel repair. The work involves removal of deficient concrete street panels, replacement with new concrete, and associated site work such as asphalt replacement, landscaping, sprinkler repairs, material hauling, and traffic‑control adjustments. The contract ceiling is $1,125,000; the award went to CHATO’S CONCRETE, LLC with a winning bid of $1,001,386. The solicitation required pre‑qualification in Category 1F(2) Concrete Roadway Paving at the $1.5 M level and set a 30 % Small Business Enterprise participation goal. Bids were submitted electronically via BidNet, with a pre‑bid meeting on March 10, 2026, questions due March 17, 2026, and bid opening on April 7, 2026. The project is expected to be completed within roughly 120 days once mobilized.
• Scope: Demolition of sidewalks, curbs, ADA ramps; new concrete pavement (6‑12″ thickness); utility adjustments; landscaping restoration; traffic‑control device installation.
• Financials: Max contract value $1.125 M; awarded bid $1.001 M; Textura admixture fee $6,435.
• Requirements: Pre‑qualification at $1.5 M level, 30 % SBE participation, prevailing‑wage compliance, bid bond, insurance, and electronic submission only.