The City of Washougal has awarded a contract to Blackline Inc. for the 2023 Slurry Seal Piggyback project. The contract includes the furnishing of all materials, labor, tools, machinery, and implements necessary for the construction and installation of slurry seal improvements. The contract price is $70,846.75, and the work is expected to be completed by December 31, 2023. The contract includes provisions for payment, indemnity, and termination. Some key points of the contract include:
• The contractor is responsible for furnishing all materials, labor, tools, machinery, and implements necessary for the construction and installation of slurry seal improvements.
• The contract price is $70,846.75, and the work is expected to be completed by December 31, 2023.
• The contractor is required to maintain insurance, including general aggregate, completed operations aggregate, and automobile liability.
• The contractor is responsible for paying all laborers, workers, or mechanics employed by it or by any subcontractor in the work of this contract at the prevailing rate of wage for hours worked.
• The contract includes provisions for payment, indemnity, and termination.