This opportunity covers comprehensive post‑disaster repairs and upgrades to the Main Power Room and the electrical systems serving Garage 2 at the Central Yard of the Sewerage and Water Board of New Orleans. The work includes demolition, removal and replacement of doors, walls, electrical equipment, service and feeder conductors, new underground duct‑bank installation, HVAC unit installation, interior and exterior painting, handrail repairs, and the replacement of lighting, CCTV, data/telephone, fire‑alarm, and public‑address systems. The scope is extensive, encompassing both civil/structural and specialty electrical/mechanical trades, funded largely through FEMA disaster‑recovery allocations.
• Complete electrical rehabilitation of the main power room (service entrance, feeder upgrades, new conduit, equipment replacement).
• Full mechanical upgrade of the power‑room HVAC system and associated civil works (door/wall repairs, painting, handrail work).
• Electrical and low‑voltage system replacement for Garage 2, including lighting, CCTV, data/telephone, fire alarm, and PA system, plus new underground duct‑bank linking to the power room.
• Project total estimated at roughly $1.3 million (bid total) to $2.25 million (engineer’s estimate plus contingencies).