The Due West Road at SR92 Realignment Project involves realigning the current side street stop-controlled intersection of Due West Road at SR92. The new alignment will move the western portion of Due West Road 680ft south of the current intersection and a traffic signal will be installed at the new intersection with SR92. The existing Due West alignment will be barricaded and the remaining roadway will be used as a local access road for adjacent properties. Key aspects of the project include:
* Realignment of the Due West Road at SR92 intersection
* Installation of a traffic signal at the new intersection
* Barricading of the existing Due West alignment
* Use of the remaining roadway as a local access road
* Compliance with Georgia Laws and regulations
* Adherence to the Georgia Department of Transportation Standard Specification for Construction of Roads and Bridges
* Performance and payment bonds required for 100% of the contract amount
* Early completion incentive of $638 per calendar day