This solicitation calls for the design‑build construction of a 4,000‑ton fabric‑covered salt storage building in Westerville, Ohio. The contractor will provide all labor, materials, and related site work, including concrete walls and slab, a reinforced‑concrete pad, LED lighting, heavy‑duty asphalt paving, grading, utilities, erosion‑control BMPs, and turf installation. The work must be completed within 160 consecutive days from the Notice to Proceed, with a 30‑day punch‑list period thereafter. The project is subject to Ohio prevailing‑wage rules, domestic‑steel requirements, a 5 % EDGE‑program participation goal, and strict bid‑guaranty and bonding requirements.
• Scope: cast‑in‑place concrete walls (≈ 12 ft high), concrete pad, LED lighting, asphalt paving, site grading, utilities (storm‑sewer, sanitary, electrical), erosion‑control and turf.
• Contract sum estimate: roughly $1.5 million (base bid); contractor responsible for all labor, materials, and subcontractor compliance.
• Key compliance: prevailing‑wage, domestic‑steel, drug‑free safety program, nondiscrimination, and EDGE diversity participation.
• Schedule: bid deadline 15 July 2026; 160‑day construction window; original bid guaranty required plus original guaranty mailed within 3 business days after deadline.
• Location: 4730 E. Dublin‑Granville Rd., Westerville, Franklin County, Ohio.