This project modernizes a 20‑block stretch of Rancho Vista Boulevard in Palmdale, CA, to bring it into full ADA compliance and close existing sidewalk gaps. The work includes demolition, concrete paving, curb‑and‑gutter replacement, installation of new sidewalks, detached retaining walls, multiple handicap‑ramp replacements, utility coordination, traffic‑control management, and associated storm‑water BMPs. The contract is funded by a CDBG grant and requires compliance with Davis‑Bacon prevailing‑wage rates, HUD Section 3 goals, and Buy‑America requirements.
• Install 8,000 sf of 4.5‑ft‑wide PCC sidewalk and 25,500 sf of 7.5‑ft‑wide PCC sidewalk.
• Construct 5 new PCC commercial driveways, replace 1,000 lf of curb‑and‑gutter, and build a 700‑lf detached retaining wall.
• Provide 36 ADA‑compliant handicap ramps, utility adjustments, traffic‑control per MUTCD for 35 working days, and a storm‑water pollution prevention plan.
• Project must be completed within 35 working days after notice to proceed; requires 10 % bid bond, 100 % performance/payment bonds, and extensive reporting (daily labor reports, monthly CDBG utilization reports, etc.).