The project involves creating two negative pressure patient isolation rooms at Delray Health. The work includes selective demolition, mechanical alteration, installation of new ductwork, and relocation of existing monitoring systems. The contractor must provide all necessary labor, equipment, and materials to complete the project within 90 calendar days from the notice to proceed. The project requires compliance with the Florida Building Code and other applicable standards.
Key features of the project include:
* Creation of two negative pressure patient isolation rooms
* Selective demolition and mechanical alteration
* Installation of new ductwork and relocation of existing monitoring systems
* Compliance with the Florida Building Code and other applicable standards
* Project duration: 90 calendar days
* Liquidated damages: $120 per day for failure to complete the project on time
Attached files
Contact
Washington Molina(Facilities Systems Project Manager)
You found this one too late. Don't find the next one too late.
Bid Banana searches open government bids across all 50 states, updated daily. Save a search once and we email you your new matches, daily or weekly, while there is still time to win them.