The City of Santa Ana is seeking qualified contractors to perform a comprehensive street‑repair program on Wright Street and Wilshire Avenue. The scope includes full removal and replacement of existing asphalt and concrete pavements, installation of new PCC sidewalks, curb ramps, longitudinal and cross‑gutters, utility frame adjustments, new water‑meter and valve frames, concrete‑filled steel bollards, and all required traffic‑control and striping. The work must commence within 45 working days after the Notice to Proceed and be completed within that same 45‑day window, with liquidated damages of $5,810 per calendar day for overruns. Bidders must submit an electronic bid plus required hard‑copy originals (ownership affidavit, bid bond, non‑collusion affidavit).
• Scope: Excavation, grading, asphalt concrete placement, Portland cement concrete (sidewalks, curb ramps, gutters), utility adjustments, signage, and traffic‑control plan.
• Schedule: Bid due 18 Nov 2026 2 PM; work must start within 45 working days of NTP and finish in 45 working days.
• Financials: Estimated contract value $1.88 M; bid bond 10 % of bid, 100 % performance & payment bonds, warranty bond per contract size.
• Compliance: Prevailing‑wage, CARB fleet compliance, CWA labor‑hour goal, CALGreen waste‑recycling, OSHA safety, and required ESCP.
• Submission: Electronic via PlanetBids plus sealed hard‑copy originals mailed or couriered to the City’s Public Works office.