The Broughton Road Bridge Replacement project in Clay County, KS involves the complete removal of an existing bridge and construction of a new structure with associated earthwork, concrete, steel, and site restoration. The scope includes extensive excavation, compaction, rock removal, concrete placement, steel reinforcement, pile driving, riprap placement, approach pavement, guard rail installation, and associated erosion control and traffic management. Bids are sealed and must be submitted by the deadline, with the project awarded as a single prime contract on a lump‑sum and unit‑price basis.
• Removal of existing bridge and construction of a new bridge structure.
• Major quantities: 2,658 CY excavation, 329 CY concrete, 70,480 lbs reinforcing steel, 1,332 LF steel piles, 1,188 CY riprap, 242 SY approach pavement, among others.
• All work will be performed under a single prime contract; bid security and prevailing‑wage exemptions apply.