The contract is for the abatement and demolition of 1GL2, 1GL3, 1FT7, 1FT8, and S14 at TSTC in Waco, Texas. The contract was awarded to Albo Construction LLC for $95,530.00 USD. The work includes the removal and disposal of asbestos-containing materials, and the subsequent cleaning of contaminated areas. The contract requires the contractor to comply with all applicable federal, state, and local regulations. The contractor must also provide a HUB Subcontracting Plan, as the contract exceeds $100,000.
• The contract requires the contractor to perform the work in accordance with the latest edition of TSTC's Uniform General Conditions.
• The contractor must provide proof of all required licenses and certifications.
• The contractor must respond to notifications to plan and schedule services within two business days of the initial request made by TSTC.
• The contractor shall maintain a traffic barricade of caution tape installed approx. 42” above finished floor unless others are stated above.
• All debris removal and cost of disposal shall be the responsibility of the contractor.
• The contractor shall clean trash, debris, and sweep work area daily.