The contract is for road improvements to CR 145 and CR 152 in Smith County, Texas. The project includes cement treatment of existing base and surface material, HMAC overlay, and all necessary appurtenances. The contract was awarded to Texana Land & Asphalt for $742,597.10. The contractor is to commence work within five calendar days after written notice and complete the work within 100 calendar days.
• The contract includes provisions for payment, commencement, and completion of the work.
• The contractor is responsible for furnishing all necessary materials, supplies, machinery, equipment, tools, superintendence, labor, insurance, and other accessories and services necessary to complete the construction.
• The contract includes a corporate seal and signature from the contractor's president.
• The contract is subject to the General Provisions, Special Provisions, Plans, and other drawings and printed or written explanatory matter thereof, and the Technical Specifications and Addenda thereto.