The contract is for the Overlay and Pavement Restoration Project 2021, which involves grinding and overlaying existing asphalt pavement, utility adjustments, and other minor improvements. The engineer's estimate for the project is between $800,000 and $1.3 million. The contract was awarded through a public bid process, with multiple bidders participating. The project manager is Abe Santos, and the bid contact is Angela Carlson.
• The project involves grinding and overlaying approximately 46,000 square yards of existing asphalt pavement.
• Utility adjustments, raised pavement markers, channelization, and other minor improvements are also included in the project.
• The engineer's estimate for the project is between $800,000 and $1.3 million.
• The contract was awarded through a public bid process, with multiple bidders participating.
• The project manager is Abe Santos, and the bid contact is Angela Carlson.