The contract is for the replacement of the Keene Hall Roof at Eastern Kentucky University. The work includes furnishing all labor, materials, equipment, and services necessary for the complete project. The contract was awarded to The Bri-Den Company, Inc. and ABR Construction, Inc. The estimated total bid for the project is $843,000.00 and $920,000.00, respectively. The project is expected to start on 5/1/2023 and 3/1/2023, and end on 7/22/2023 and 6/1/2023, respectively. Some key features of the contract include:
• The contract is a Construction Invitation to Bid (CITB) type.
• The project requires a mandatory pre-bid meeting.
• The contractor must provide surety bonds.
• The contract has a substantial completion date of 6/01/2023 and a final completion date of 6/16/2023.
• Liquidated damages are $200 until substantial completion and $100 until final completion.