The Evergreen Way Sidewalk Connection Project involves the construction of a sidewalk, curb, and gutter, as well as stormwater improvements, pavement restoration, signing, and striping. The project is located on Evergreen Way between 42nd Street and the western-most driveway of the George Schmid Memorial Park. The contract was awarded to Colf Construction LLC, and the project is expected to be completed within 60 calendar days. The engineer's estimate for the project is $488,465. The project is funded by a Transportation Improvement Board (TIB) grant.
Some key points to consider:
* The project requires the payment of prevailing wages.
* The contractor must comply with all federal, state, and local laws and regulations.
* The contractor must provide a bid bond and a performance bond.
* The contractor must have a City of Washougal Business and Occupation License.
* The contractor must be registered with the Department of Homeland Security E-Verify program.
* The project involves the construction of a sidewalk, curb, and gutter, as well as stormwater improvements, pavement restoration, signing, and striping.
* The project is located on Evergreen Way between 42nd Street and the western-most driveway of the George Schmid Memorial Park.
* The contract was awarded to Colf Construction LLC.
* The project is expected to be completed within 60 calendar days.
* The engineer's estimate for the project is $488,465.
* The project is funded by a Transportation Improvement Board (TIB) grant.