This contract concerns the replacement of lighting fixtures in five designated rooms and associated operating rooms within the Ronald Reagan UCLA Medical Center. The scope includes demolition of existing fixtures, installation of new lighting, related electrical work, and ancillary tasks such as painting and steel support where needed. The university’s Capital Programs office awarded lump‑sum contracts to two primary general contractors, who in turn engage multiple specialty subcontractors for electrical, demolition, painting, and steel work. The total awarded value across all packages is roughly $2 million, reflecting a mid‑size facility‑upgrade project.
• Primary work: Electrical lighting replacement in clinical/operating‑room environments.
• Awarded to: MZN Construction, Inc. (≈ $628 k) and M T M Construction, Inc. (≈ $686 k), with additional subcontractor packages totaling ≈ $658 k.
• Procurement: Competitive bid process with bid opening on 31 Mar 2026; award issued 27 May 2026.