This contract concerns the demolition of a nuisance structure located at 4400 Government Blvd., Mobile, AL. The City of Mobile’s Municipal Enforcement Department issued a Request for Bids (RFB ME‑007‑23) with an addendum clarifying full “wet demolition” requirements, utility caps, complete foundation removal, debris disposal to an approved C&D landfill, and extensive environmental controls (erosion, sediment, dust, and grassing). Bidders submitted sealed bids by 2:15 PM on August 23, 2023; the low bid of US$51,000 was submitted by Complete Demolition Services LLC, which later appears as the awardee. The contractor must complete the work within 60 calendar days from the notice to proceed and is subject to liquidated damages of $250 per day for any delay beyond the 30‑day post‑completion grace period. Licensing (Alabama BC or D) and bonding (performance and labor‑material) are required, and DBE documentation must be submitted.
• Scope: full wet demolition, utility termination, foundation removal, debris disposal, and site restoration.
• Schedule: bids due Aug 23 2023; work to be finished within 60 days after notice to proceed.
• Requirements: Alabama contractor license (BC/D), performance & labor‑material bonds, demolition permit, environmental controls, DBE paperwork.