Description
The Bruce Road Reconstruction project involves the reconstruction and widening of a segment of Bruce Road from State Route 32 to Skyway. The project includes the replacement of a bridge over Little Chico Creek with a new 4-lane bridge, and the construction of a concrete roadway, landscaped center median, roadway lighting, buffered bike lanes, dedicated left turn lanes, and storm drainage improvements. The project is funded by the State Infill Infrastructure Grant (IIG) and local funds. The engineer's estimate for the project is approximately $30,100,000. The project has a 300 working day duration. Key features of the project include:
• Reconstruction and widening of Bruce Road
• Replacement of the bridge over Little Chico Creek
• Construction of a new 4-lane bridge
• Concrete roadway and landscaped center median
• Roadway lighting and buffered bike lanes
• Dedicated left turn lanes and storm drainage improvements
The project requires the payment of prevailing wage rates and is subject to state contract nondiscrimination and compliance requirements.