The Municipality of Skagway awarded a construction contract for a new 60‑by‑100‑foot metal composting building. Island Contractors Inc. won the award as the low‑bidder, receiving an annual contract value of $330,158. The project involves erecting a pre‑engineered metal structure on an existing concrete foundation, using insulated roof and wall panels supplied by the municipality, and following detailed erection drawings prepared by Vacro Pruden and Kingspan.
• Scope: erection of a pre‑engineered metal building (60’ × 100’) with insulated panels on an existing foundation.
• Procurement: open competition with two bidders; award to low‑bidder (Island Contractors Inc.).
• Financials: awarded contract value $330,158 per year; original bids $456,800 (Island) and $539,224 (Dawson).
• Timeline: bids opened Oct 29 2019; intent‑to‑award notice issued Dec 13 2019; protest period ended Dec 20 2019.