The City of Madison awarded a mid‑size public‑works contract (Contract 8809) for the South Charter Street Alley Assessment District. The scope encompasses storm‑sewer pipe installation, utility relocation, extensive excavation, removal and replacement of existing concrete curb, gutter, and sidewalk, asphalt paving, erosion‑control measures, traffic‑control device provision, contaminated‑soil excavation and disposal, and final site restoration. The contract is a best‑value, lump‑sum award to Parisi Construction, LLC for a total value of $148,733, with work scheduled to begin early June 2026 and be completed by the end of June 2026.
• Storm‑sewer infrastructure: ~103 ft of 12‑in. PVC pipe, inlet structures, and tap.
• Site work: excavation, root‑cutting, removal of curb/gutter, sidewalks, bollards, and contaminated‑soil handling.
• Pavement & curb work: new concrete curb & gutter, asphalt terrace, sidewalk reconstruction.
• Supporting services: traffic‑control devices, erosion‑control matting, de‑watering, street sweeping, and environmental oversight.