This contract awards the installation of a new owner‑furnished modular power plant, a heat‑recovery system, and a comprehensive upgrade of the existing overhead electric distribution network in Rampart, Alaska. The scope includes civil earthwork, retaining walls, helix piles, geomembranes, utility pole and transformer installation, Arctic pipe, surge arresters, grounding, and full testing/commissioning. The work is funded jointly by the Denali Commission and State appropriations, with a bid bond of 5 % and performance/payment bonds of 100 % of contract price.
• Modular plant and heat‑recovery system installation – full field assembly, connection, and start‑up.
• Electrical utility upgrades – new poles, wood poles, Arctic pipe, overhead lines, liquid‑filled transformers, and associated hardware.
• Civil/structural works – excavation, de‑watering, retaining walls, geomembranes, and site preparation.
• Strict quality‑control, testing, and warranty requirements, with liquidated damages of $500/day (max $10 K).