This contract involves a nuisance abatement project that requires the complete wet demolition of all structures at 2661 Betbeze Street, Mobile, AL, followed by utility disconnection and capping, site remediation, erosion control, and final site stabilization. The contractor must submit detailed documentation, including before‑and‑after photos, waste‑shipment records, insurance certificates, and proof of compliance with environmental regulations. The work must be completed within a 30‑day performance window after receipt of a Notice to Proceed, with liquidated damages for late completion.
• Wet demolition of all structures, footings, and slabs, with dust control measures.
• Utility line disconnection and capping (sewer, water, gas) to satisfy city and utility agencies.
• Environmental compliance: sediment/erosion control, lead‑based paint and asbestos handling, and final seeding/soil stabilization.
• Mandatory post‑completion documentation: newspaper notice of final completion, lien releases, insurance, and photographic evidence.