The contract is for the medium voltage infrastructure improvements at New Mexico State University. The project involves the installation of medium voltage infrastructure from S25-180 to the edge of pavement by Kent Hall, as well as several alternate bids for additional work. The contract was awarded to multiple vendors, including RCI Power and Lighting Inc, Carver Electric Company, Inc., Bixby Electric Inc., and Corbins Service Electric LLC. The contract duration is 240 calendar days from the notice to proceed, and the contract value is estimated to be around $162,389.00 to $340,051.00, depending on the vendor and the scope of work.
• The contract includes a base bid and several alternate bids for additional work.
• The contract requires the vendors to provide a 5% bid bond and to comply with all applicable state laws and regulations.
• The contract includes a liquidated damages clause for late completion.
• The contract requires the vendors to provide a performance and payment bond for subcontractors.
• The contract includes a clause for the resolution of disputes.