This contract awards the design, fabrication, and delivery of a 40‑ft, 15‑ft‑wide by 7‑ft‑high precast concrete split‑box culvert for Menzel Lake Road in Snohomish County, Washington. The County solicited bids through a formal sealed‑bid process, evaluated on lowest price, and selected H2 Precast as the sole vendor. The contract is a firm‑fixed‑price agreement valued at roughly $95,580, with delivery required by July 22, 2019.
• Scope: design, PE‑stamped calculations, fabrication, and FOB‑destination delivery of a precast culvert (skewed 30° ends).
• Requirements: WSDOT‑approved supplier status, detailed submittals (shop drawings, mix design, reinforcement data), and two recent project references.
• Timeline: bid deadline May 7 2019, award May 13 2019, final shipment July 22 2019.