The contract is for the construction of the Meyergrove Stormwater Detention Basin for the Harris County Flood Control District. The project involves the construction of a detention basin to reduce flood damage in the area. The contract was awarded to Solid Bridge Construction, the low bidder, for a total amount of $5,359,510. The project is funded by FEMA grant funds and is expected to reduce the impact of street flooding in the Braeswood Boulevard corridor. The key features of the project include:
* Construction of a detention basin to reduce flood damage
* Funding provided by FEMA grant funds
* Expected to reduce the impact of street flooding in the Braeswood Boulevard corridor
* Project is located in the City of Houston, within Precinct 1, east of I-610 along N. Braeswood Boulevard, and adjacent to Brays Bayou
* The project is part of a larger effort to prevent flooding in the area, which has previously experienced flooding multiple times.