The Municipality of Skagway solicited bids for the construction of a prefabricated “Pan‑Abode” kit cabin (Project 320) at the Dyea Campground. The owner supplies the cabin kit; the contractor must provide all hardware, foundation materials, transportation, site preparation, installation, permits, insurance, and compliance with building codes and COVID‑19 protocols. The award went to Doland Construction for a lump‑sum price of $56,450. The bid deadline was 15 Sept 2020, with a final completion deadline of mid‑October 2020 and liquidated damages of up to $1,000 per day for delay. Key points include:
• Scope: foundation, hardware, transport, installation, permitting, and full compliance with Alaska building and health regulations.
• Awards: Single‑source award to Doland Construction; no bond required (contract value under $150 k, bonding exemption possible).
• Schedule: Bids due 15 Sept 2020; notice of intent to award 18 Sept 2020; project to be finished by mid‑October 2020.