The Pennsylvania State University (Office of the Physical Plan) awarded a feasibility‑study contract to Perkins & Will for the design of a new ~40,000 gsf Animal Diagnostic Laboratory (ADL) at the University Park campus. The study will assess site conditions, develop space‑program requirements, generate planning concepts, produce a high‑level cost estimate, and deliver a final feasibility report by November 2021. The procurement followed a standard LOI → RFP → short‑list → interview process, culminating in a single‑vendor award. No monetary value, contract term, or vendor contact details were disclosed.
• Scope: site assessment, program development, concept planning, cost estimating, schedule, final report.
• Performance standards: must meet PSU’s High‑Performance Building Design Standards (ASHRAE 90.1‑2010, ASHRAE 189.1‑2011) and achieve at least LEED Certified.
• Timeline: RFP issued May 14 2021, proposals due June 4 2021, short‑list announced June 18 2021, interviews July 13 2021, award July 16 2021, study to be completed November 2021.